6. ITPs, weld records and the data pack

Put an inspection and test plan on the BOM and sign it off on each work order, keep your WPS register and welder qualifications, record each weld, and print the data pack and certificate of conformance to hand over.

Where it is

The inspection and test plan

On a draft BOM revision, Inspection and test plan lists the checks every work order from it is signed off against. Each point has a type (Hold, Witness, Review or Surveillance), the check, the acceptance criteria and a reference (the standard and clause, or the drawing).

On the work order, Sign… each point Pass, Fail (say what) or N/A (say why), with a Record reference (a dimensional report, a mill certificate number). An order can't be completed while a hold point isn't passed or marked N/A.

Procedures and welders

Manufacturing → Welding keeps your WPS register (process, standard, revision) and each Welder's Qualification, with when it Expires. Expired ones show red, and ones expiring within 30 days amber. Keep it current: a welder whose qualification had expired by the weld date can't be recorded against a weld.

Weld records

On the work order, under Welds and data pack, Record a weld: the Joint mark on the drawing, the WPS, the Welder, the category (SP or GP, AS/NZS 1554.1), the consumable batch, the Visual inspection, and any NDT with its method, result and report. Set the job's Construction category (AS/NZS 5131) there too.

Handing it over

  • Data pack prints the manufacturer's data report: materials with batch and heat numbers and whether the mill certificate is on file, the ITP as signed, the weld register, the QC sign-offs and any non-conformances, ending in a signature block. No prices.
  • Certificate of conformance, in the order's actions, prints the certificate for a finished order.

Save either as a PDF from the print dialog and send it with the job.

That's the course

Pass the quiz for Silver. Gold comes from real work: 10 QC or first-article checks you sign off within 90 days, or a manager who watches you take a part from quote to data pack.

Lesson 6 of 6 in Quoting and quality for fabricators. Previous: 5. Non-conformances: raise, decide, close.

Related guides