1. Your rates: what every quote is priced from

Manufacturing → Quoting rates holds what a fabrication quote is priced from: a sell rate for each work centre, cut speeds by material and thickness, your finishes, and the margin, utilisation, scrap, quantity breaks and rounding. Get these right first.

Where it is

Who this is for: whoever prices work (estimators, the owner, a sales engineer) and whoever answers for quality (a quality lead, a production manager). Lessons 1 to 3 are quoting, 4 to 6 are quality.

Every price BuildTrack gives you for a made part comes from one page: Manufacturing → Quoting rates. The AI never sets a price, and nor does anyone typing a number into a line. If a quote looks wrong, the answer is almost always on this page.

Everyone with manufacturing access can read it; changing it needs the Edit settings permission. Nothing here is a cost: a work centre's cost rate stays on Work centres, behind the cost permission.

Rate cards

One row per active work centre:

  • Sell $/hour: what you charge for an hour of that machine or bay.
  • Setup min: the setup a part gets on that centre unless its routing says otherwise.
  • Minimum $: the least you charge for using it on a quote line.

Press Save on the row.

Cut speeds

For each cutter, one row per Material and Thickness mm: the Feed mm/min and the Pierce s, from the machine's feed chart. Paste a feed chart takes rows straight from a spreadsheet. A thickness with no row uses the nearest one for that material; a material with no row at all can't be priced, and the quote says so in amber instead of guessing low.

Finishes

Powder coat, galvanising, anodising: each Priced per m², per kg or each, with a Rate $ and a Minimum $. Done by is In house or the sublet product of the contractor who does it, and Days is what it adds to the lead time.

Quote settings

  • Margin % goes on what you buy in at cost (material and hardware). Work-centre time and finishes are already sell prices, so no margin is added to them.
  • Sheet utilisation %: how much of a sheet becomes parts; the rest is priced in.
  • Scrap %: extra units cut to allow for rejects.
  • Quantity breaks: the quantities every part is priced at, for example 1, 10, 50. The first is always 1.
  • Round prices, always up, and a Minimum charge $ per quote line.

Your sheet and plate

The material price comes from your own stock products. On each sheet or plate product, Edit and fill in Material: form, material, grade and thickness. Without it, a part can't be cut from that sheet.